JEL Maintenance Pte Ltd

Current Projects

PROJECT CLIENT LOCATION DURATION SCOPE
H2GEN Port Dickson Linde Engineering (Malaysia) Sdn Bhd Port Dickson, Negeri Sembilan Jul 2019 - Aug 2020 General Construction Civil and Mechanical Work Including Supply and Laying of NG pipeline at HRC Port Dickson
MMCC 2242MW CCGT Power Plant, Melaka Hyundai Engineering Malaysia Sdn Bhd Melaka Nov 2018 - May 2021 Mechanical work (Turbine & BOP, EN)
MMCC 2242MW CCGT Power Plant, Melaka Hyundai Engineering Malaysia Sdn Bhd Melaka Apr 2019 to Jul 2020 Mechanical work (HRSG)
Track 4A 1440MW CCGT Power Plant, Pasir Gudang Johor Southern Power Generation Sdn Bhd Pasir Gudang, Johor Mar 2018 - Nov 2019 General mechanical construction works
Reformer Installation Works (P03) Técnidas Reunidas (Malaysia) Pengerang, Johor Feb 2017 – Jan 2018 Mechanical and Piping Fabrication and Erection Works
ASU RAPID (R14) Linde Engineering (Malaysia) Pengerang, Johor Mar 2017 – Jan 2019 Civil Engineering Works
BASF Petronas Nitrogen Supply Project Air Products (Malaysia) Sdn Bhd Gebeng, Pahang Jan 2017 – May 2017 Mechanical and Piping, Electrical and Instrumentation, Insulation and Scaffolding works
Jimah East Power 2 x 1000MW Coal Fired Power Plant Ishi Power Lukut, Negeri Sembilan Dec 2016 – Apr 2019 Mechanical & Electrical Instrumentation and Controls Installation, NDT, Inspection, Testing & Pre-commissioning Works
RAPID Steam Cracker Project (SCC) Toyo Engineering & Construction Pengerang,Johor Aug 2016 – Jul 2018 Piping, Steel Structure Installation and Painting in Compressor Area
MY1008 Pengerang Cogen Plant (PCP) Siemens Malaysia Sdn Bhd Pengerang,Johor Nov 2015 – May 2017 Erection Works for Heat Recovery Steam Generator (HRSG) and Turboset
Fast Track 3A Project (Manjung 5, 1x1000MW Coal Fired Power Plant) Daelim Manjung,Perak Aug 2015 – Feb 2017 STG Installation Works
Fast Track 3A Project (Manjung 5, 1x1000MW Coal Fired Power Plant) Daelim Manjung,Perak Oct 2014 – Mar 2017 Mechanical Work Package 1 (Boiler Mechanical)